Project Update: July 2011


8 July 2011

. INDUSTRIAL PAVILION MASTERPLAN INFRASTRUCTURE
New Work

Removal of Industrial Pavilion roofing

Removal of Industrial Pavilion roofing including rafters and purlins

Demolition of Frank Nicklin Building

Demolition of Frank Nicklin Building.  Works to be completed by mid July 2011

Ongoing Work

Installation of structural steel

Installation of structural steel on Ekka Plaza facade

Final demolition of Frank Nicklin Building

Final demolition of Frank Nicklin Building

Upcoming Work Demobilisation of site for Ekka preparation at the end of July 2011 Proposed Earthworks to commence late July 2011