December 2011

8 December, 2011

AREA UPDATE
INDUSTRIAL PAVILION

New Work

  • Start of Stage 3 suspended slab pour

Ongoing Work

  • Bulk and detailed excavation, pouring columns and footings and laying in-ground services

Upcoming Work

  • Concrete pour of further suspended slabs
08.12.11 (1) 08.12.11 (2)

15 December, 2011

AREA UPDATE
INDUSTRIAL PAVILION

New Work

  • Stage 6 of column and retaining walls concrete pour

Ongoing Work

  • Level 1 - Pour 3  of the suspended slab
  • Bulk and detail excavation, pouring columns and footings and laying in-ground services

Upcoming Work

  • Concrete pour of further suspended slabs
15.12.11 Image 15.12.11 Image 2