Project Updates: January, 2012

6 January, 2012

AREA UPDATE
LITTLE WATER STREET INFRASTRUCTURE ENABLING WORKS

New Work

  • Pouring of base slabs and installation of pre-cast box culverts to excavation area for manhole chambers
  • Installation of support structure to existing stormwater culvert
  • Installation of support to existing sewer line crossing triple culverts

Ongoing Work

  • Excavation of single and  triple cell culverts
Upcoming Work
  • Manhole construction works
6.1.12
6.1.12 (1)

9 January, 2012

AREA UPDATE
INDUSTRIAL PAVILION

New Work

  • Level 1 - Pour 6 of the suspended slab

Ongoing Work

  • Bulk and detail excavation, pouring columns and footings' pour and laying inground services
Upcoming Work
  • Concrete pour of further suspended slabs
9.1.12
9.1.12 (1)

30 January, 2012

AREA UPDATE
INDUSTRIAL PAVILION

New Work

  • Level 1 - Pour 6 of the suspended slab

Ongoing Work

  • Pouring of columns and footings and further work on the inground services
Upcoming Work
  • Concrete pour of further suspended slabs. Fabrication and installation of structural steel to kitchen area
30.1.12
30.1.12 (1)