Project Updates: July, 2013

4 July, 2013

AREA UPDATE
ROYAL INTERNATIONAL CONVENTION CENTRE - The Plaza

Upcoming

  • Planting trees
  • Installing irrigation
  • Paving
  • Form reo pour of stairs
  • Construction of the Porte Cohere Canopy
  • General metalwork of balustrades and handrails
Work is  continuing on the Plaza this week alongside the 2013 Caravan and Camping Show
Landscaping
In ground services
Block work
General metalwor
The Plaza July 4

The Plaza July 4 b

11 July, 2013

AREA UPDATE
ROYAL INTERNATIONAL CONVENTION CENTRE - The Plaza

Ongoing

  • Install paving
  • Soft landscaping
  • Metalwork
  • Roof work on port cohere
  • Electrical and hydraulic installation
Work is  continuing on the Plaza this week alongside the 2013 Caravan and Camping Show
Landscaping
In ground services
Block work
General metalwor
The Plaza July 11
The Plaza July 11 b

24 July, 2013

AREA UPDATE
ROYAL INTERNATIONAL CONVENTION CENTRE - The Plaza

Ongoing

  • Planting and mulching
  • Final clean
  • Paving
  • Handrails and balustrades
  • Signage
Work is  continuing on the Plaza this week alongside the 2013 Caravan and Camping Show
Landscaping
In ground services
Block work
General metalwor
The Plaza July 24 a
The Plaza July 24 b