Project Updates: June, 2012

4 June, 2012

AREA UPDATE
LITTLE WATER STREET INFRASTRUCTURE ENABLING WORKS

New Work

  • Completion of structural beams and wall to the inlet chamber

Ongoing Work

  • As all culverts and the trunk sewer pipes are installed, backfilling work continues

Upcoming Work

  • Installation of pre-cast concrete lids and steel grates to top of Inlet Chamber

 

01 02

5 June, 2012

AREA UPDATE
ROYAL INTERNATIONAL CONVENTION CENTRE

New Work

  • Main Hall structural steel

Ongoing Work

  • Foyer structural steel utilities
Upcoming Work
  • Asphalt works in lower car park, interior finishes

Foyer roof steel

Foyer Roof Steel

Main Hall Steel

Main Hall Steel

Phase 2 bracing steel

Phase 2 Bracing Steel


25 June, 2012

AREA UPDATE
LITTLE WATER STREET INFRASTRUCTURE ENABLING WORKS

Ongoing Work

  • Ekka preparation works
Completed Work
  • All culverts installed and trunk sewer completed
1 2
3

26 June, 2012

AREA UPDATE
ROYAL INTERNATIONAL CONVENTION CENTRE

New Work

  • Mezzanine level works
    Lower car park asphalt
  • Mezzanine level works
  • Lower car park asphalt

Ongoing Work

  • Ground floor installation of utilities
  • Phase 2 steel
  • Acoustic panel installation
Upcoming Work
  • Lower rooms interior finishes
  • Further structural steel
  • Mezzanine level slab installation

Foyer Structural Steel

Foyer Structural Steel

Future Entry area

Future Entry Area

Heritage Facade in Foyer

Heritage Facade in Foyer