. INDUSTRIAL PAVILION

MASTERPLAN INFRASTRUCTURE

New Work

Removal Roof Sheeting

Initial removal of roof sheeting from the Industrial Pavilion to allow temporary structural steel works to proceed.

Demolition Buildings 4 5 6

Demolition of Buildings 4,5 and 6 to make way for major infrastructure works for the regeneration project

 

Removal of the interior walls and flooring of the Frank Nicklin Building

Ongoing Work

Initial Asbestos Removal Footing support for temporary structural steel to Ekka Plaza Facade

Slab and footing removal in and around demolition area.

Ongoing internal strip out of Frank Nicklin Building.

Upcoming Work

Steel pylons will be bolted onto concrete bases in order to support the retained heritage facade of the Industrial Pavilion along Gregory terrace and Ekka Plaza

 

Removal works - Frank Nicklin Building

 

30 May 2011

. INDUSTRIAL PAVILION

MASTERPLAN INFRASTRUCTURE

New Work

Steel works being erected

Steel work has been erected to support the Gregory Terrace heritage facade. This will be completed shortly.

Removal Frank Nicklin Building

Slab preparation ready for upcoming Caravan and Camping Show 8 - 14 June 2011

Ongoing Work

Removal of internal fit out

Removal of northern sky lights and removal of internal fit out of existing mezzanine levels

Frank Nicklin Building removal

Ongoing internal strip-out of Frank Nicklin Building

Upcoming Work

Removal of saw tooth roof

 

Steel pylons will be bolted onto concrete bases to support the retained heritage facade of the Industrial Pavilion along Gregory Terrace and Ekka Plaza

Removal works - Frank Nicklin Building