Project Updates: October, 2012

3 October, 2012

AREA UPDATE
ROYAL INTERNATIONAL CONVENTION CENTRE

Ongoing Work

  • Popout Works continue with the steel installed and the glazing framed out
  • Foyer Roof sheeting installation
  • Door frame installation and wall rough works
  • Wall sheeting
  • Installation of ceiling hangers
  • Roof sheeting and cladding
  • Removal of temporary bracing removed
  • Façade restoration, painting, rendering and brick repair
  • Main hall steel, roofing and cladding

Upcoming Work

Lower rooms interior finishes
Further structural steel
Mezzanine level slab installation
  • Sheeting, wall and floor finishes
  • Services to be installed
  • Façade restoration and door installation
  • Installation of louvers and doors
  • Back wall cladding

 

3 October 1

Main Entrance Popout

 

3 October 2

Foyer Roof

3 October 3

RNA Offices

3 October 4

Main Hall

3 October 5

RNA Offices

3 October 6

Ekka Plaza Heritage Facade

3 October 7

Gregory Terrace Heritage Facade

3 October 8

Main Hall

26 October, 2012

AREA UPDATE
ROYAL INTERNATIONAL CONVENTION CENTRE

Ongoing Work

  • Installation of cladding, window frames and window glazing
  • RNA Offices - Ongoing sheeting, wall and floor finishes
  • Services to be installed.
  • Ongoing wall sheeting.
  • Installation of operable wallOngoing roof cladding
  • Façade restoration and installation of entry doors and windows
  • Installation of loading bay door frame
  • Ongoing brickwork restorationGlass bricks to be replaced.
  • Steel window frame installation
  • Glazing of steel framed windows.Ongoing  brickwork restoration
  • Conference meeting rooms - framing and sheeting,  installation of  high level fire service and air conditioning services

26 October 1

Main Entrance to RICC

26 October 2

RNA Offices

26 October 3

Main Hall

26 October 4

RICC Roof

26 October 5

Facade Restoration

26 October 6

Facade Restoration

26 October 7

Facade Restoration

26 October 8

Facade Restoration

26 October 9

Conference Rooms